Veymandoo Land Reclamation Completed in 23 Days
DHDhiyares – 2 months ago
Heads up!
This is an AI-generated summary and may contain inaccuracies. The original article should be consulted for complete accuracy.
President Dr. Mohamed Muizzu announced today the successful completion of the Veymandoo land reclamation project. The practical work for reclaiming land in Veymandoo began on March 12, 2026, and was fully completed on April 4, 2026. A total of 27 hectares of land were reclaimed, using 882,693 cubic meters of sand. The entire project was finished in just 23 days and was carried out by Maldives Airports Company Limited (MACL).